Infomation
of Daily Production |
30/11/2007
at 7.30 AM. the OCEAN EAGLE of GREEK nationality, it has
74,761DWT and ever entered Cam Pha port.. This is the biggest cargo
vessel that has ever entered a port in Vietnam, The
OCEAN EAGLE is 224.9m in length and 32.26m in
width, the draft line of 14.1m with 7 holds made and 4 cranes 40T each
will receive 55,000 Tons of coal (34,000
tons of coal dust and 21,000 tons of lump coal ) for SSM,
a Holland customer in Europe. It is estimated that our
productivity reaches 18 million tons in this year, the
highest number compared with other ports. The fact that the OCEAN EAGLE
landed at the new whaft of Cam Pha Port has marked an
important point in the investment task of the
Vinacomin Group in general, and the Vinacomin-Port
Company in particular, in the economy-increasing
strategy of the Port.
|
|
26/12/2006
10.30-Cam Pha Port. The Vinacomin celebrated
the loading of the 36 millionth ton of coal in 2006 to
Chu Lai- a vessel of the Middle Coal Company, which has
received 4,400 tons of coal at berth. To participate in
the celebration, there comes Mr. Doan Van Kien, the
Deputy Secretary of the Party Civil Affairs Committee
and General Director together with many leaders of the
Vinacomin. On behalf of the Vinacomin, Mr. Doan Thien
Ngon has sent flowers and fine arts made of coal to the
officers and seafarers working on the vessel.
|
|
13/11/2006 According
to a recent decision of The
Vietnam National Coal - Mineral Industries Group, since
01/11/2006, all of the vessels' shipment in HonGai has
been moved to HonNet and ABay anchorages. On 13/11/2006
the coal output of the Vinacomin-Port Company reached a
record number of 50,328 T for 12 vessels.
|
|
10/11/2006 The Vinacomin-Port
Company has fulfilled the plan based on the legal Order
No.530 QĐ-KHZ issued on 22/02/2005 by the Vietnam
National Coal - Mineral Industries Group for 2006 with
the total output of 29,758,000 T, about 101.7% as
compared with the planned output of 29,248,000 T
|
14/08/2006 The
Board of Management of the Vinacomin-Port Co. held a
discussion with the USDG 3-member team, led by
Mr.Michael Christopher- Lieutenant Commander, in their
visit to some of the Vietnamese seaports in order to
exchange information on the security measures taken in
compliance with the ISPS Code. After having listened to
the report on Port and Port Facility Security of the
Vinacomin-Port Co., the USDG made a trip visit to the
berths of Cam Pha Port. The US side made good comments
on the implementation of the port's security
regulations. The discussion took place in a friendship
and mutual understanding atmosphere
|
22/06/2006 The 71,761DWT Go Public made a good landfall at
the new wharf- Cam Pha Port. Following the successful reception of the 70,000DWT
Baramundi on 13 Feb at Cam Pha Port, the Vinacomin-Port
Company( of the Vietnam National Coal-Mineral Industries
Group) at 14p.m today, 22 June welcomed the landfall
of the 71,761DWT Go Public. This is the biggest cargo
vessel that has ever entered a port in Vietnam( bigger
vessels have to stay at the anchorage for
cargo-handling). The Go Public of Bahamas nationality, 223.7m in length and 32.2m in
width, is a craneless, panamax-typed vessel with 7
holds. The most interesting fact is that the vessel has
been received at the new wharf of Cam Pha Port, a
construction in the project
|
|
| "
Cam Pha Port-
Its Improvement and Extension", which has been recently
completed and brought in to use by Vinacomin Group. The
new wharf, built under the most modern concrete-filled
foundation pile technology, is 250m long, 50m long and
9m deep, capable to receive over 70,000 DWT vessels. The
Go Public will load up to 67,500 tons of coal (49,500
tons of coal dust and 18,000 tons of lump coal ) for SSM,
a Holland customer in Europe. The fact that the Go Public
landed at the new whaft of Cam Pha Port has marked an
important point in the investment task of the
Vinacomin Group in general, and the Vinacomin-Port
Company in particular, in the economy-increasing
strategy of the Port.
|
24/03/2006
In
harmony with the exciting atmosphere of the youth over
the country in holding activities celebrating the
Foundation Day of the HCM Communist Youth Union, welcoming the
2006 Month of Action, the Youth Union of the company,
under the leadership of the standing Party Committee,
solemnly held the 75th Anniversary of the Foundation Day
of the Youth Union. In the anniversary, many mementoes 'For the Youth' were given to former cadres who have made
good records in the youth movements of the HCM
Communist Youth Union. Also in this
occasion, the awards of the competition on Finding about the 75
Years of the Glorious History of the HCM Communist Youth
Union were offered. |
|
22/03/2006 After
more than one year under construction, the project on
the improvement and extension of Cam Pha Port has been
basically completed. Vinamarine has agreed by
texts to postpone the deadline for the new wharf to be
brought into use. This morning, the Vinacomin-Port
Company has welcomed the first vessel, the STAR
POLLUX, to port. This vessel, of Greek nationality,
43,775 MT, 190m long, 32.5 wide, with 4 cranes 30T each
will receive 22,000 Tons of coal at berth and the
rest off-shore at Hon Net. |
01/03/2006 The Opening Ceremony of the Communicative English class
for port management and exploitation was held at
the big hall with the participation of Mr. Doan
Thien Ngon, Secretary of the communist party,
Director of the Company; Mrs. Nguyen Thi Thuy and Mr.
Nguyen Manh Quan from the Personnel Department
together with 50 learners from different rooms in the
company. This is the first English class held and taught
by a teacher in concurrent post of the company. |
24/01/2006 The Company Youth Union held the meeting concluding
its tasks and movements in the year
2005 and planning those for the year 2006. The year 2005 has
witnessed lots of important political events as the
communist party meetings of all levels preparing for the
10th National Party Congress, 69 years of the
Traditional Day of the mine working people 12/11, the
presence of the Vietnam National Coal-Mineral Industries
Group before the public... |
|
07.00 am-13/02/2006 The MV
BARAMUNDI,70,000 DWT of PANAMA safely
got alongside the main wharf. This has been the MV with
the biggest tonnage to Cam Pha Port and even to Vietnam so far. It was built in
1994, 225m in length, 32m in width, the draft line of
13.3m with 7 holds, 4 cranes, 30T each. To receive
such big vessels, the Vinacomin-Port Company
has continuously invested on the improvement of the
port for years, especially the extension of 250m of the
old port towards the downstream and the dredging of the
channel from Buoy zero. The BARAMUNDI will receive
32,000T of coal dust( 17,400T of size No 6 and 14,800T
of size No 8) at berth, the rest will be loaded at Hon
Net, preparing for the journey to Japan, for the
customer SUMITOMO. This signals a new year of growth of Vinacomin-Port
Company |
27/01/2006
Mr. Doan van Kien, Deputy Secretary of the Party Staff,
General Director of the Vietnam National Coal-Mineral
Industries Group came to visit the Vinacomin -Port
Company on the
occasion of the new year to come. |
08.00 am- 13/01/2006 The 2006 Meeting of working people and officials was
solemnly held at the Big Hall of the Company. To participate in and to conduct
the meeting, there
came leaders of the VINACOMIN and 112 out of 120 delegates representing the
working people from all units of the company. The meeting carried out the
review on the implementation of the 2005 resolution and
set up the 2006 plans. The meeting also conduct the
summation on the emulation movements of the 2005 plan;
gave rewards to out standing groups and individuals and
initiated the new movements for the year 2006. The whole
meeting has agreed to pass the resolution and determined
to fulfill the expected tasks |

|
01/01/2006 : 07h00
The Vessel CHULAI,
4,505 DWT, of Vietnam nationality and
The Vessel MARIA C, 45,205 DWT, of Panama nationality
came into Port to load the first tones of coal of the
year 2006. The Board of Management of the Port and Coal
Trading Company got on board and sent them best wishes
on the new year occasion. |
30/12/2005 : 08h00
Under the guidance of VINACOAL, the Port and Coal
Trading Company, in accordance with the main office and
sub-divisions of VINACOAL, Cua Ong Coal Preparation
Company held
the Ceremony welcoming the 30 millionth
tone of coal consumed in the year 2005. There came to
the ceremony, Mr. Nguyen Van Quynh - Provincial
Secretary; Chairman of the Quang Ninh Provincial People's
Committee, Mr. Nguyen Van Long - Party Civil Affairs
Committee; Chief of Management Board of VINACOAL, |
 |
| Mr.
Doan Van Kien - Vice of the Civil Affairs Party Committee; General Director of VINACOAL, Mr. Do Thong -
Secretary of City Party Committee, Mr. Do Minh Tuan -
Chairman of Cam Pha People's Committee, Mr. Doan Thien
Ngon - Secretary of Party Committee; Director of the
Port and Coal Trading Company, Mr. Hoang Lam Chinh -
Director of Cua Ong Coal Preparation and Directors from
Coal business, Purchasers & Counterparts around
Quang Ninh |
24/12/2005 : 20h30
The Cam
Pha
Port Enterprise and The Port and Coal Trading Company
held the Christmas Night on Cong Tay Island for more
than 40 seafarers of 5 Vessels (GOLDEN
TRUST No.2, ORANDA, JING CHANG SHOU 28, GOLDEN TRUST
No.3, HONG LI) from Hon Net anchorage and the
main Port. The Christmas Celebration was warm and full
of friendship with Vietnamese, Chinese and English
famous songs. The dancing party brought everyone
together and really created good impression on the
seafarers and through which showed the hospitality of
the staff-members of Cam Pha Port in general and the
Enterprise in particular. |
News issued |
|
|
 |